Data CentersTop story
Musk says two more SpaceXAI data centers in Southaven will start up by December
Gun Range is expected to hold about 220,000 chips, Spam about 200,000
Source: The Tennessee Tribune
View as table
| Value | |
|---|---|
| Gun Range | 220K |
| Spam | 200K |
If you cross the state line into Southaven, expect dust. Elon Musk says SpaceXAI is building two more data centers there, and the Daily Memphian reports dozens of dump trucks and concrete trucks working at the sites at Tulane and Stateline roads.
Musk says Gun Range should be running by the end of November and Spam in December. The Tennessee Tribune notes those dates are his projections and haven't been independently confirmed. Gun Range was a police and fire training facility. Spam was a Hormel warehouse.
- Both sites: Southaven, Mississippi
- Colossus 2 goal: about 1.2 million Blackwell chips by end of 2026
- Traffic: congestion on Stateline Road has grown near the power plant
Southaven Mayor Darren Musselwhite calls the campus "a good thing for Southaven." In Memphis, the City Council approved a pause on new data center permitting. It doesn't stop existing facilities from operating.
Southaven's tax take, buyout offer and Memphis's permit pause by the numbers
- $63 million
- a year for DeSoto County Schools, DeSoto County and Southaven
- 400+
- nearby homes and businesses SpaceXAI is offering to buy
- 135 days
- Memphis pause on new data center permitting
Sources: Action News 5, The Tennessee Tribune