Musk says two more SpaceXAI data centers near Southaven will be running by December
Musk says Spam will hold about 200,000 chips and Gun Range about 220,000
Source: DeSoto County News
View as table
| Value | |
|---|---|
| Gun Range | 220K |
| Spam | 200K |
Elon Musk says two more SpaceXAI data centers are going up beside the Colossus 2 campus in Southaven, and Action News 5 reports he confirmed it. The Daily Memphian described dust clouding the area from about a half mile out Thursday, as dozens of dump trucks and cement trucks worked the sites at Tulane and Stateline roads.
Musk named them Gun Range, for a former local police department gun range, and Spam, for a building once used for Hormel products. Yes, one of them is called Spam. DeSoto County News says the chip counts come from his posts and haven't been independently verified.
- Gun Range: running by the end of November, Musk says
- Spam: running in December, Musk says
Memphis City Council recently failed to pass a one-year moratorium and passed a 135-day pause on data centers instead. Across the line, contractors have filed liens worth more than $220 million in DeSoto County over the project.
The buildout comes with big numbers on both sides of the state line
- 1.2 million
- Nvidia chips expected on the Colossus 2 campus by year's end
- $220 million
- and more in liens filed in DeSoto County
- 135 days
- for the data center pause Memphis council passed